How is takt time calculated?
Takt time = Net Available Production Time ÷ Customer Demand. Net Available Production Time is the Shift Duration minus Planned Non-Production Time. With 450 minutes (27,000 seconds) available and a demand of 420 units, takt time is 27,000 ÷ 420 = 64.3 seconds per unit.
What goes into Planned Non-Production Time?
Everything planned in which the process is not meant to produce: breaks, cleaning, team meetings, planned maintenance and similar periods. Unplanned stops such as breakdowns are not included here. They are a loss against the pace, not time you removed in advance.
Is takt time the same as cycle time?
No. Takt time is the pace the customer demand needs. Cycle time is the interval your process actually delivers finished units. Comparing the two tells you whether the process is, on paper, faster or slower than the demand requires.
If my cycle time is faster than takt, will I always meet demand?
Not necessarily. The comparison assumes the process delivers a unit every observed cycle time, all the time, with no stoppages, defects or other losses. Real processes lose time, so many teams plan to run faster than takt to leave room for losses. The result is a pace comparison, not a production forecast.
Why are the shortfall and the output shown differently?
Customers need whole units, so the potential surplus or shortfall counts only complete units. The theoretical output is kept as a decimal as supporting information, for example 397.1 units, of which 397 are complete.
What does Additional Time Required mean?
It is the extra production time that would be needed to make the full demand at the observed cycle time, if there were no other losses: Demand × Cycle Time ÷ 60 − Net Available Production Time, and never below zero. It is an idealised figure, not a prediction or guaranteed overtime.
What if demand changes or I make several products?
This version works with one product, or one consistently defined output unit, and one demand figure. If the mix or the demand changes, calculate each case separately. Product mixes, changeovers, batch operations and parallel machines need additional analysis that this calculator does not do.
How does takt time relate to OEE?
Takt time says how fast you need to go. OEE shows how much of your planned time was truly productive, once stops, slow running and defects are taken out. A process that looks fast enough against takt can still fall short if it has low OEE. You can measure that with the free OEE calculator.
Is my data stored or sent anywhere?
No. The calculation runs in your browser and nothing you type is sent to our servers.